- Detail
TSP/TSP Name: 131537896 - WBI Energy Transmission, Inc.
Notice ID: 7373
Notice Type: Loc Chg
Notice Stat Desc: Initiate
Prior Notice:
Critical: N
Post D/T: 10/16/2024 @ 9:07 AM
Notice Eff D/T: 10/16/2024 @ 9:07 AM
Notice End D/T: 11/30/2024 @ 5:00 PM
Reqrd Rsp Desc: No response required
Rsp D/T:

Subject: Line Section Name Change
Notice Text: To provide better communication of system availability, WBI Energy Transmission, Inc will be splitting Line Section 26 into two separate line sections. Effective November 1, 2024, Line Section 26 will encompass Manning to the Golva Compressor Station; new Line Section 35 will be from Golva Compressor Station to Belle Creek Junction.

The following point locations will be moving from Line Section 26 to Line Section 35:

Delivery Points:
Point 01012 MDU-Tran.Line(26)MTZ41
Point 01013 MDU-Trans.Line(26)MTZ39
Point 04017 Baker Booster Field Fuel

Receipt Points:
Point 04015 Baker Grasslands
Point 04016 Baker Booster
(Rolls to Point 04015 Baker Grasslands)

Please call the Scheduling Department at 701-530-1630 if you have any questions.

*** All references to Time are stated for the Central Time Zone.

If you have any questions or comments regarding this information, please e-mail Market Services.
Copyright © - WBI Energy Transmission, Inc. Legal Disclosure Notice