Planned Service Outage - Detail
TSP/TSP Name: 131537896 - WBI Energy Transmission, Inc.
Notice ID: 3864
Notice Type: Maint/Planned
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Post D/T: 7/15/2026 3:37 PM
Notice Eff D/T: 8/17/2026 9:00 AM
Notice End D/T: 8/21/2026 5:00 PM
Reqrd Rsp Desc: No response required
Rsp D/T:

Subject: Line Section 17 Mainline Maintenance
Notice Text: Planned maintenance will be performed on a portion of the mainline in Line Section 17.

This maintenance affects the physical transfer between Cabin Creek and Elk Basin Compressor Stations, transfer capacity for the duration of this maintenance will be 0 dkt/day.

Flow west of the Cabin Creek Compressor Station onto Line Sections 16 and 17 will be limited to the delivery demand in these Line Sections.

Flow east of the Elk Basin Compressor Station onto Line Section 18 will be limited to the delivery demand in Line Section 18, this includes WBI Point ID's; #03895 - MDU-Hardin Industrial, #03900 - MDU-Hardin Border, and #03880 MDU-Crow Agency Border.

Information will be updated in the event conditions change.
Map: Line Section 17 Maintenance 7-15-26.png

* WBI Transmission reserves the right to revise the Planned Maintenance Schedule from time to time as either operating or maintenance conditions change.

*** All references to Time are stated for the Central Time Zone.

If you have any questions regarding this schedule, please contact a Transportation Services Analyst at 701-530-1630.