Notice Text:
|
A hydrotest will be performed on a portion of Line Section 06 (Morgan Creek Compressor Station to Williston Compressor Station) from Gas Day August 10, 2026 to Gas Day August 14, 2026.
Natural gas transferring to and from Line Sections 06 and 30 will be unavailable for the duration of this maintenance, Williston Compressor Station will be the transfer cutoff point.
Service to these WBI Points will be available for the duration of the hydrotest:
#01410 - MDU-Williston Border #01420 - MDU-Williston Airport Border #01430 - MDU-Williston North Border #01431 - MDU-Williston East Border #01436 - Missouri Ridge Field Fuel
This hydrotest has the potential to increase line pressures in Line Sections 6, 7, 25, 30, 32 and WBI Point #0904 McKenzie Plant / Fort Buford.
Information will be updated in the event conditions change.
|